Project Requirements
Mid-Western Regional Council require a level area for a sports training complex. The project area has hard rock ground conditions that prevented pier and post retaining wall installation. Therefore, an ‘L-Block’ system was required to overcome the ground condition challenges.
Morestone Solution
Morestone was engaged by Mid-Western Regional Council to prepare the footing area for the L-Block wall system by levelling and compacting the footing material to meet construction specifications. Morestone also worked with a crane company to ensure the L-Blocks were correctly positioned.
As shown in the photos, Morestone’s construction of Stage 1 was successful and ready for backfilling to the L-Block wall. Specific work completed by Morestone included:
- Preparation of footings
- Coordinating placement of L Block panels
- Sealing of joints
- Installation of drainage line